Cherie’s Blacktown Renovation No.2
THE STORY:
Top Renovator, Cherie Barber is challenged with updating a drab, dated 1970’s bathroom that’s seen better days. Home owner Abhishek Sharma has just purchased this investment property and has a budget of only $2,500, all said and done, to transform his bathroom space. Whilst the bathroom is currently functional, the bathroom lacks any ounce of personality and the current bathtub is not suitable for a family who will live in the property, once rented.
Abhi has called in top gun Cherie for a quick cosmetic refresh. With a lot of DIY work, Cherie & Abhi team up to prove that it is possible to transform your bathroom on a small budget.
RENOVATION STRATEGY:
Improve the appearance of an existing 1970’s bathroom through a low budget ($2,500) cosmetic refurbishment (no structural changes) including:
- Removal of dated fixtures & fittings.
- Remove small bath tub & install new standard size bath.
- Tile paint existing wall tiles.
- Install new tiles on one side of the bathroom as a feature.
- DIY re-painting of walls & ceiling.
- Installation of new floor tiles.
- Updating existing bathroom lighting;
- Installation of new toilet, vanity, mirror, fixtures & fittings.
COST SUMMARY:
Property Value Before Renovation: $410,000.00
Renovation Spend: $2,562.99
Renovation Timeframe: 4 Days
Property Breakeven Point: $412,562.99
Property Value – Post Renovation: $420,000.00
Profit Margin (After Reno Costs): $7,437.01
EXPENSE ITEM | |||
BATH RELOCATION | New Bath (Secondhand) | $ 40.00 | |
Structural Pine for Bath Frame (2 x 2.4m) | $ 14.64 | ||
Carpentry Labour To Install Bath Frame & Villaboard (Done by Abhi -Owner) | $ – | ||
1 Sheet of Villaboard 1200 x 2400 | $ 28.83 | ||
Chrome Bath Waste | $ – | ||
Aluminum Tile Angle for Bath | $ 15.00 | ||
Bath Taps | $ 33.00 | ||
Shower Head & Taps | $ 39.00 | ||
Glass Shower Screen | $ 110.00 | ||
Carpentry Labour To Install Glass Shower Screen (Done by Abhi -Owner) | $ – | ||
SUB-TOTAL: BATH | $ 280.47 | ||
TOILET RELOCATION | 2nd Hand Toilet (Second Hand from Gumtree) | $ 70.00 | |
1 Tube x White Silicone | $ 9.00 | ||
SUB-TOTAL: TOILET RELOCATION | $ 79.00 | ||
NEW FLOOR | Waterproofing | $ 189.00 | |
5 Tubes x Selleys Flexiseal Sealant @$10.43 each | $ 52.15 | ||
SUB-TOTAL: FLOOR | $ 241.15 | ||
VANITY REPLACEMENT | 2nd Hand Vanity (Secondhand) | $ 71.00 | |
Vanity Taps & Head | $ 30.00 | ||
Chrome Vanity Waste | $ 8.00 | ||
900 x 900 Mirror | $ 40.00 | ||
Double Sided Foam Tape for Mirror | $ 5.93 | ||
SUB-TOTAL: VANITY REPLACEMENT | $ 154.93 | ||
HOLE IN WALL | Timber (Use Leftovers) | $ – | |
Villaboard (Use Leftovers) | $ – | ||
Carpentry Labour – 30 Mins (Done by Abbi (Owner) | $ – | ||
SUB-TOTAL: HOLE IN WALL | $ – | ||
TILING & FLOORS | Wall tiles – 4m2 x $10m2 | $ 40.00 | |
Floor tiles – 4m2 x $10m2 | $ 40.00 | ||
Tiling Labour – Floor & Wall Tiles
(Done DIY by Abhi (Owner) & Cherie Barber) |
$ – | ||
Tile Spacers | $ 8.90 | ||
EXPENSE ITEM | |||
White Knight Tile & Laminate Primer | $ 44.90 | ||
White Knight Tile Paint | $ 46.50 | ||
Tile Adhesive – 20 kilo drum | $ 73.50 | ||
Grout for Floor & Wall Tiles | $ 20.00 | ||
SUB-TOTAL: TILING | $ 273.80 | ||
ELECTRICAL | 2 new downlights @ $15.00 each | $ 30.00 | |
1 x Pendant Feature Light | $ 39.00 | ||
Globe for Pendant Light | $ 1.50 | ||
Electrical Labour – 2 Hour Minimum | $ 275.00 | ||
SUB-TOTAL: ELECTRICAL | $ 345.50 | ||
PLUMBING | Plumbing Labour – 8 Hours @$76 ph + GST | $ 668.80 | |
Plumbing Materials | $ 292.12 | ||
$ 960.92 | |||
PAINT | 1 x 1 Litre Ceiling Paint | $ 7.95 | |
1 x 1 Litre Wall Paint | $ | ||
1 x 1 Litre Gloss Door Paint | $ 31.08 | ||
Painting Labour – DIY (Done by Abhi (Owner) & Cherie Barber) | $ – | ||
SUB-TOTAL: PAINT | $ 69.03 | ||
MISCELLANEOUS | Rubbish Removal | $ – | |
Door Handle | $ 25.97 | ||
Floor Waste | $ 8.00 | ||
2 x Chrome Spice Racks @$2.99 each | $ 5.98 | ||
1 Can x White Spray Paint | $ 9.24 | ||
Towel Rail x 2 @$29 each | $ 58.00 | ||
Shower Soap Dish | $ 24.00 | ||
Toilet Roll Holder | $ 27.00 | ||
Carpentry Labour – 1 Hour
(Done by Abhi – Owner) |
– | ||
SUB-TOTAL: MISCELLANEOUS | $ 158.19 | ||
TOTAL COST OF WORKS: | $ 2,562.99 |
Last Updated: 5th February 2018.